HUD CHUMS, CAIVRS and LOCCS: Unisys COBOL to Java in the cloud
How TSRI, Salient CRGT and HUD used Technology Modernization Fund money to move critical federal systems off a Unisys mainframe, transforming more than 1.3 million lines of code at 99.67% automation.
Executive summary
One of the first federal modernizations funded by the TMF
Using money from the Technology Modernization Fund (TMF) under the Modernizing Government Technology Act, disbursed by the General Services Administration, HUD sought to modernize several of its remaining critical systems on a legacy Unisys mainframe written in COBOL with hierarchical DMS and relational RDMS databases.
Salient CRGT engaged TSRI to provide automated transformation and refactoring for four sequential modernization projects, transforming more than 1.3 million lines of code at 99.67% automation.
The systems moved from a Unisys mainframe to modern Java in the Azure cloud, and the DMS and RDMS databases were transformed to Microsoft SQL Server. Software Maintenance Agreements now support the systems in production.
01 · Challenge
Decades-old systems, a dwindling workforce
The TMF, authorized in 2017, came from a specific need: many U.S. government systems run decades-old applications on mainframes, some written in languages custom-developed for the agency’s mission. By the early 2010s, two factors had emerged: these applications could no longer survive in their current form with a dwindling workforce, and cloud computing could increase capacity when necessary and improve the security of mission-critical applications.
HUD recognized early that the TMF gave it the opportunity to secure budget and approvals from the GSA for sequential modernizations of four critical applications on the same Unisys mainframe, all written in Unisys COBOL with proprietary DMS and RDMS databases:
CHUMS
Computerized Home Underwriting Management System: processes Single Family mortgage insurance applications, with thousands of daily transactions.
CAIVRS
HUD’s credit application system. The F42 credit reporting system was also modernized, then decommissioned before production.
LOCCS
Line of Credit Control System: a disbursement and cash management system distributing over $28 billion a year.
02 · Selection
Why Salient CRGT chose TSRI
Salient CRGT had exhaustively researched approaches to migrating these systems and determined that TSRI’s code conversion process best fit the project’s critical success factors. TSRI and Salient CRGT jointly funded a prototype, transforming a portion of CHUMS, to prove the project’s viability to HUD. With more than 25 years refining its automated approach, TSRI could deliver high accuracy and minimal disruption to HUD’s daily operations.
03 · Solution
Untangling DMS, then transforming at scale
Because of the way DMS is structured, it required commands within a discrete description file written in COBOL to work with any new functionality. Those dependencies had to be removed first, so TSRI contracted with DMS specialist PracTrans. Janus Studio® then transformed the COBOL into Java and the DMS database into a Microsoft SQL Server relational database.
TSRI began with CHUMS, which took approximately eight months to prepare and transform, about 800,000 lines at 99.67% automation. Every project included Application Blueprint® documentation and automated refactoring to consolidate duplicate records and remove dead and redundant code. To meet the federal PMD and Checkstyle quality standards, TSRI tuned its refactoring engine and used fully and semi-automated refactoring. Functional enhancements during the project needed minimal code freeze, and full parallel regression testing ran between the mainframe and Azure.
Who did what
- 01 · PRIME FUNDER
GSA
Primary funding source
- 02 · CLIENT
HUD
End user of the applications
- 03 · PRIME INTEGRATOR
Salient CRGT
Contracted through GSA
- 04 · CODE CONVERSION
TSRI
Automated transformation
- 05 · DMS SPECIALIST
PracTrans
Removed DMS dependencies
A go-live faster than planned
Go-live was planned for an extended federal holiday weekend to avoid downtime. The teams allocated three days; implementation and full data migration finished in 14 hours, and the system went live with only minor issues reported by more than 26,000 users on day one. The LOCCS go-live saw similar results, with more than $300 million in payments made in the first week without issue.
04 · Results
A model for federal modernization
Many entities watched this project because, in many ways, it served as a proof of concept for the federal government’s path to future modernizations. HUD was among the first to use TMF funding this way, and the GSA wanted to see how far the funding could go and how quickly projects could be completed. While the project began in 2019, the COVID-19 pandemic showed how critical these modernizations have become.
Transformed across four projects
Unisys COBOL to Java in the Azure cloud.
Near-100% automation
With fully and semi-automated refactoring to PMD and Checkstyle standards.
Go-live and full data migration
Against three days allocated.
LOCCS payments
Made in the first week without issue.
Tuning from CHUMS carried into every later project, saving HUD time and money. With a Software Maintenance Agreement in place, TSRI continues to support the updated systems in production, including framework updates and maintenance.